The first unit of the Sebzor hydroelectric power station is promised to be launched in June 2025

The commissioning of the first unit of the Sebzor hydroelectric power station with a capacity of 3.6 MW will take place in June 2025, this was announced during a working trip of the Minister of Energy and Water Resources of Tajikistan Daler Juma to the Roshtkal district of the Gorno-Badakhshan Autonomous Region.

Первый агрегат Себзорской ГЭС обещают запустить в июне 2025 года

«The minister got acquainted with the progress of construction of the Sebzor hydroelectric power station, talked with engineers and project officials and discussed the progress of the work», — reports the press center of the Ministry of Energy of the Republic of Tatarstan.

«According to officials, to date, construction work at the site has been completed by 85%, the necessary measures are being taken to commission the first unit of the 3.6 MW power plant in June of this year», — the press center reported.

Sebzor Hydroelectric Power Station — a project of the Government of Tajikistan, implemented with financial and technical support from the European Union and the Government of Germany through the German Bank, KfW, the United States Agency for International Development, the Swiss Secretariat for Economic Affairs and the World Bank.

Construction of a hydroelectric power station on the Shokhdara River began in 2015, the project provides for 3 hydraulic units.

The small hydroelectric power station «Sebzor», with a capacity of 11 MW, will have the ability to provide electricity to tens of thousands of local residents, as well as export electricity to the border areas of Afghanistan.

The construction of the hydroelectric power station is being carried out by the Tajik Installation Department «Gidroelektromontazh» (TMU GEM).

Let us remind you that the launch of the first unit of the hydroelectric power station «Sebzor» was first planned until 2024, then its launch was scheduled for 2024.